Sampling type - Defines how the samples are calculated
Valuation mode - Defines rules for accepting or rejecting characteristics or samples
Both sampling type and valuation mode forms a sampling procedure
Hence Sampling procedure determines the rules to calculate samples and accept or rejects samples during result recording
Sampling procedure can be used at task list level or at material level
In the material master QM view, the sampling procedure can be assigned but the cons of doing this is the sampling procedure that is assigned will be applicable to only that material
To create a sampling procedure, tcode used is QDV1
Steps to create:
- Enter the sampling procedure name
- Enter the usage of the inspection plan and the status should be released in order to use the inspection plan, if the plan is no longer in use then the deletion flag can be set. Enter from lot size and to lot size, this can be used when you want the system to assign inspection plan for different lot size. Next click on operations to assign MIC and sampling procedure
- In operations enter work center (A work center is a place where all the inspection activities such as testing, visual inspection, documentation, sampling activities takes place tcode to create CRQ1), Control key(QM01 - Internal QM operation - Used for lab testing, allows result recording) and select the operation and click on inspection characteristics
- MAINTAIN QM SETTINGS FOR PLANT UK11 - I received this error while trying to assign MIC and sampling procedure. To resolve this, go to SIMG -> Quality management -> Basic Settings->Maintain Settings at Plant Level
- Create an inspection lot and assign task list and samples to the lot in order to proceed with results recording and UD









No comments: